We are replacing the existing culvert in Perth Street, South Toowoomba with a modern, higher‑capacity structure designed to better convey severe weather events. The new culvert will improve safety, flood immunity and local road network reliability for motorists, pedestrians and nearby residents.
Timber elements were discovered during excavation works in late April 2026. Construction was paused while an archaeological investigation was completed.
Early findings suggest the timber may be part of a historic creek crossing dating back to the 19th century.
We will continue to share updates with the community as more information becomes available.
Start date
Construction commenced in mid‑April 2026 and was paused while archaeological investigations were completed.
Construction resumed on Monday 13 July 202 and is currently under way.
Completion date
The target completion date is March 2027, weather and construction conditions permitting. The project timeline has been extended due to the heritage discovery and recent wet weather.
During construction works expect:
The emptying activity will be completed in line with relevant environmental management requirements to protect the waterway and surrounding area.
While the project is under way, access to Willows Health & Fitness Centre and 7-Eleven remains available.
We encourage residents to continue supporting these local businesses throughout construction. A small detour can make a big difference.
The project is funded with the Australian Government under the Emergency Response Fund.