You can change your development approval during, or after, your appeal period.
During the appeal process, submit your change request to us. You need to pay the fee and include any supporting information. If you need more time, you can ask us to suspend the appeal period. This will give you an extra 20 business days.
You can also make changes after the appeal period ends. Depending on the scope of the change, it may be a "minor" or an "other" change.
Minor changes must meet the requirements of Schedule 1: Substantially different development of the Development Assessment Rules.
You must make "minor" and "other" change applications directly to us as the "responsible entity" under per section 78 of the Planning Act.
Download and complete the change application form.
If you need help or advice, contact a Technical Advice Officer.