A Community Benefit Agreement (CBA) deed is a legal document that records the agreement between a renewable energy project developer and us.
Once both parties sign the deed, the agreement becomes legally binding. It explains what the developer has agreed to do, what benefits they will provide and how the agreement will be managed throughout the life of the project. All CBA deeds will be published once finalised and signed.
Our Renewable Energy Community Benefit Agreement Policy(PDF, 283KB) explains how CBAs are negotiated and managed for renewable energy projects. Each deed is prepared for a specific project. While the policy sets the overall approach, the details of each deed are based on the project's needs and impacts, including social impacts.
Signed CBAs
Cattle Creek Wind Farm – RWE Cattle Creek Onshore Wind Pty Ltd Community Benefit Agreement(PDF, 1MB)
Community input
Community members can share their views at different stages of the process:
- During the Social Impact Assessmet (SIA) process: the project developer must consult with people and groups who may be affected by the project. This helps identify community priorities, potential impacts and ways to manage them.
- Through community benefit liaison groups: community members can share local knowledge, provide feedback and help identify priorities for community benefit funding.
- As part of the Queensland Government's development assessment process: when a project is publicly notified, information about the project and how to make a submission is available through the SARA Submissions Portal.
Further information
CBA deed commitments
A CBA usually includes three main parts:
Mandatory mitigation - Actions the project developer must take to manage social impacts. This may include community engagement, local jobs, transport, environmental impacts, land and water management, community safety and handling complaints.
Legacy benefits - Financial contributions the project developer must make to the community benefit fund, including when payments must be made.
We manage the community benefit fund and make funding decisions based on community feedback, local priorities and the requirements of the policy.
Funding from a renewable energy project must be used within that project's local benefit area or provide a clear benefit to the communities in that area. It can't be used for unrelated projects in other parts of the Toowoomba Region.
Governance and accountability - The processes that help the agreement work over time, including reporting, monitoring, reviews, dispute resolution and managing changes to the project or agreement.
Monitoring and enforcement of commitments
The CBA includes reporting and monitoring requirements so we can check that commitments are being delivered. It also includes processes for resolving issues or disagreements if they occur.
Some agreements may include additional safeguards, such as financial security arrangements. The focus is on identifying and resolving issues early, with legal action available if needed.
Length of a deed
A deed is intended to operate over the relevant life of the project, which may be 30 years or more.
Commitments apply at different stages of a project. Some commitments are most important during construction, when impacts on the community are often at their highest. Other commitments, such as contributions to the community benefit fund, may continue throughout the life of the project.
Review process
CBAs are long-term agreements and may need to adapt as circumstances change. To support this, they include review processes that allow the agreement to be assessed at key stages or when significant changes occur.
These reviews help keep commitments practical, relevant and effective throughout the life of the project, without needing to predict every situation that may arise in the future.
Community benefit fund
We manage the community benefit fund which receives funding from renewable energy project developers through their CBAs.
This funding is separate from the costs of managing project impacts. It is used to support eligible projects and initiatives that provide long-term benefits to communities connected to renewable energy developments.
Social Impact Assessment (SIA) and Social Impact Management Plan (SIMP)
A Social Impact Assessment (SIA) examines how a proposed project may affect local people and communities and identifies measures to manage potential impacts. This can include impacts on housing and accommodation, local employment and businesses, community services, health and wellbeing and the way people live and interact within their community.
A Social Impact Management Plan (SIMP) is prepared by the project developer and explains how those measures will be put into practice and monitored over time. Potentially affected communities and stakeholders will be engaged during the process.
The findings and commitments outlined in the SIA help inform the CBA deed. The deed sets out the responsibilities agreed between us and the project developer and makes those commitments legally binding.
Development approvals versus CBAs
Development approvals and CBAs work together but serve different purposes:
- A development approval sets the conditions a project must meet through the planning and approval process.
- A CBA sets out how the project developer will manage social impacts and deliver agreed benefits to the community.
The CBA does not replace the project's development approval or any other legal requirements.
The CBA and SIA occur before the development application is lodged. The project must then proceed through the applicable development assessment process.
Queensland Government assessment process
Large renewable energy projects are assessed and approved by the Queensland Government through the State Assessment and Referral Agency.
This process considers matters such as project location, noise, visual impacts, environmental requirements, bushfire management and other technical standards.
A CBA cannot change these requirements or approval conditions.
Instead, a CBA focuses on how a project may affect local people, communities, Council infrastructure and services. It can also provide long-term benefits for communities affected by renewable energy development.
We review the project's SIA and can raise local issues through the State assessment and public consultation processes.
Change of project ownership
Renewable energy projects can be sold to a new owner during their lifetime. CBAs include requirements to make sure the agreement stays in place if this happens.
If a project changes ownership, the new owner must take on the responsibilities in the agreement. This helps ensure that community benefit commitments and measures to manage impacts continue into the future.
Council and community project approvals and support
A CBA does not mean we support or oppose a renewable energy project. Renewable energy projects go through a separate development assessment process to determine whether they can be approved.
Our role in a CBA is to help represent the interests of local communities by working with project developers to manage social impacts and secure community benefits.
The CBA process is separate from any decision about whether a project is approved.
A CBA also does not show whether the community supports or opposes a renewable energy project.
We recognise that people in the community may have different views about renewable energy projects. Some people may support the opportunities these projects can bring, while others may have questions or concerns about their impacts.
The purpose of a CBA is to help manage social impacts and deliver community benefits. It is separate from the process used to assess and approve a project.
Project decommissioning
The Queensland Government requires renewable energy projects to plan for the end of a project's life. This includes removing project infrastructure, restoring the site where needed and meeting any rehabilitation requirements.
Project developers are also required to provide financial security, such as a bond or financial guarantee, to help ensure these responsibilities can be carried out.
CBAs do not replace these requirements and community benefit fund money is not used for decommissioning costs. Responsibility for decommissioning remains with the project developer throughout the life of the project.
Private commercial arrangements
Agreements between project developers and landholders are private arrangements and are separate from the CBA. These agreements do not change a project developer's responsibility to manage impacts on the wider community.
We recognise that people can be affected by a renewable energy project even if they do not host project infrastructure or receive payments from the project.
The local benefit area is based on where the project's impacts are expected to be felt, using information from the SIA. It is not determined by whether a property is part of a private agreement with the project developer.
The Renewable Energy Community Benefit Agreement Policy guides how we work with renewable energy developers to create, manage and review Community Benefit Agreements (CBAs).
The policy sets clear and consistent requirements for renewable energy projects across the Toowoomba Region. It helps ensure communities affected by renewable energy development receive benefits from these projects over the long term.
Read the Renewable Energy Community Benefit Agreement Policy(PDF, 283KB)
Purpose of the policy
In 2025, the Queensland Government introduced new requirements for some large renewable energy projects. These projects must complete a Social Impact Assessment (SIA) and enter into a CBA before they can lodge a development application.
We adopted the Renewable Energy Community Benefit Agreement Policy in November 2025 to provide a clear and consistent process for these agreements. The policy helps ensure renewable energy projects deliver lasting benefits to communities across the region.
Renewable energy projects covered by the policy
The policy applies to large renewable energy projects in Toowoomba Region that are required by the Queensland Government to complete a SIA and enter into a CBA.
This includes wind farms, solar farms, pumped hydro projects and battery energy storage projects with a generating capacity of 1 megawatt or more.
Large-scale renewable energy development is occurring across Queensland, including in the Toowoomba Region.
Renewable energy projects can include wind farms, solar farms and battery energy storage systems, together with supporting infrastructure such as substations, transmission connections, access roads and workforce accommodation.
These projects can bring significant investment, jobs and business opportunities to the Region. They can also create impacts for nearby communities and place additional pressure on housing, roads, services and other local infrastructure. Managing this growth effectively will help maximise these benefits while supporting local communities and planning for increased demand on housing, roads, services and other infrastructure.
Council's role
Our role is to help ensure these impacts are properly identified and managed and that communities hosting renewable energy development share in the long-term benefits.
We work with renewable energy project developers, communities and other levels of government to:
- identify and manage project impacts
- maximise local jobs, skills and business opportunities
- minimise additional pressure on housing, services and infrastructure
- protect community wellbeing and local amenity
- involve affected communities in discussions about local priorities
- create benefits that continue beyond the construction period.
State government involvement
The Queensland Government assesses and decides development applications for large renewable energy projects. We are not the assessment authority for these projects and are not able to approve or refuse the projects.
We review the project developer's Social Impact Assessment (SIA), negotiate and enter into a Community Benefit Agreement (CBA) before a development application is lodged, monitor that agreement once it is in place and make submissions to the State on matters affecting the Toowoomba Region.
Expectations for renewable energy developers
We expect developers to:
- engage early and genuinely with affected communities
- identify and respond to social impacts
- provide realistic and measurable commitments
- create opportunities for local workers and businesses
- communicate openly throughout construction and operation
- work collaboratively with us, communities and other stakeholders
- deliver the commitments contained in their CBA
- engage directly with traditional owners on cultural heritage and participation.