Toowoomba Regional Council (TRC) is committed to making the West and Stephen Street intersection safer for community members by undertaking important roadworks from Sunday, 8 June, 2025 until mid July.
TRC Construction and Maintenance (Infrastructure Services) portfolio spokesperson Councillor Carol Taylor said TRC had prioritised safety improvements for this busy intersection.
“We want to minimise any risks and ensure our road infrastructure is as safe as possible for our community,” Cr Taylor said.
The scheduled safety upgrades include changes to the traffic signals, traffic light phasing, pedestrian crossing facilities and improvements to the pram ramps, curb and drainage systems.
Council has taken specific planning measures to ensure the duration of construction works have minimal impact on the community.
“We are conducting night works and staging any road closures to ensure all road users, pedestrians and residents of the area are impacted as little as possible,” Cr Taylor said.
Road closures and detours will be in place throughout the duration of the works however, Council will maintain local access to residences and businesses within the closure areas.
Roadworks and road closures dates:
The following dates are subject to weather and construction conditions permitting.
Sunday 8 June (night works 6pm to 6am – conduit & pit install)
Monday 9 June (night works 6:30pm to 6am – conduit & pit install)
Wednesday 11 June to Sunday 22 June (day works – conduit & pit install)
Monday 23 June to Friday 4 July (day works – conduit & pit install)
Early July (date to be confirmed – large lighting and signals infrastructure)
Early to late July (dates to be confirmed - pram ramps, footpath resurfacing, small lighting and signals infrastructure)
“I want to thank the community for their patience during these upgrades and I also want to thank the infrastructure services team and construction crews for their continued hard work,” Cr Taylor said.
For more information, please call the Customer Service Call Centre on 131 872 and quote West and Stephen, or visit: West & Stephen Street, Harristown intersection upgrade on the TRC website.
Photo caption: A map of the staging of works for the West and Stephen Street intersection upgrade, starting Sunday 8 June to early July 2025.