A budget of $600,000 has been allocated in the 2021/22 year for the design and construction of sewer pump station upgrade works at the Creek St Sewage Pump Station. This upgrade will enable conversion from a common effluent drainage (CED) scheme to a conventional sewerage scheme.

The contract was awarded for the design and construction of the project in November 2020.

Start date

Works commenced on site end of May 2021.

Completion date

December 2021.