In 2021/22 the following culvert renewal projects will be undertaken to replace existing structures in poor condition with new structures to current standards:

 

Kingsthorpe Haden culvert renewal

A budget of $1.3 million has been assigned in 2021/22. The concept and design have been finalised in 2020/21 with the construction to be completed in 2021/22.

This project is jointly funded by Bridges Renewal Program funding from the Australian Government.

Start date (construction)

August 2021.

Targeted completion date

December 2021.

 

Clifton Allora Road culvert renewal

A budget of $250,000 has been assigned in 2021/22. The concept and design have been finalised in 2020/21 with the construction to be undertaken in 2021/22.

Start date (construction)

April 2022.

Targeted completion date

August 2022.

 

Breydons Road, Hodgson Vale culvert renewal

$250,000 has been allocated to the Breydons Road culvert renewal in the 2021/22 financial year. The concept was completed in 2021 with design, including environment approvals, and commencement of construction to be undertaken in 2021/22. Completion is scheduled in early 2022/23. 

Start date (construction)

October 2021

Targeted completion date

March 2022.

 

Newman Road, Wyreema culvert renewal

A budget of $635,000 has been assigned in 2021/22. The concept and design are to be finalised in early 2020/21 with the commencement of construction in April 2022. Completion is expected by December 2022.

This project is jointly funded with Disaster Recovery Funding Arrangements (DRFA) funding from the Australian Government.

Start date (construction)

April 2022.

Targeted completion date

December 2022.