Aerial photo of Rockville Park AFL field

The Rockville Park clubhouse amenities upgrade replaces the existing facility with a modern facility. This upgrade ensures we are able to meet the current and future demand of Rockville Park, including the emergence of female AFL within the Region.

A budget of $1.9 million for this project has been assigned in 2021/22.

Site planning was undertaken in 2018/19. 

A tender originally went for the Rockville Clubhouse and Amenities Upgrade in September 2021; however, due to market volatility and record-high demand in the construction industry, no suitable tenders were received..

An extension of time has been granted for the project to be completed across two financial years.

Start date

To be confirmed. 

Completion date

June 2023.