Millmerran pool

Following community consultation undertaken early 2021, the 60 year old community facility will be upgraded. The existing pool will be replaced with a new 50 metre pool, including pool heating. An access ramp is planned to ensure the pool is accessible to people living with a disability or limited mobility

A budget of $2.5 million has been allocated in 2021/22.

Start date

October 2021.

Target completion date

February 2022.

 

Oakey pool 

The Oakey swimming pool change room upgrade will involve the demolishment of the original change room building and a replacement will be constructed. The new facility will provide guests with access to disability friendly change rooms and toilets. 

A budget of $800,000 has been allocated in 2021/22.

Start date

October 2021.

Target completion date

February 2022.

 

Yarraman Pool

The Yarraman swimming pool change room upgrade will provide guests with access to a disability friendly amenity and connecting pathways. The change room will also include a family change room.

A budget of $350,000 has been allocated in 2021/22.

Start date

September 2021.

Expected completion date

January 2022.