Kingsthorpe & Gowrie Junction sewerage project

Pipe connection to house

The $20 million Kingsthorpe and Gowrie Junction sewerage project will be completed this year with an allocation of $0.45 million.  Project works have been in progress for 3 years to provide reticulated wastewater networks within Kingsthorpe (520 house connections) and Gowrie Junction (200 house connections). The new network replaces septic tank and household wastewater treatment systems on small lots (under 2,500 m²) for public health benefits and to support growth.

Works to be undertaken in 2017/18 to complete the project include the completion of house drain connections in Kingsthorpe, and the construction and commissioning of the Jeude Street sewage pump station, gravity connection and rising main.

Start date

November 2014.

Target completion date

Project works will be completed late 2017, weather permitting.

Stages

  1. Sewer main installation commenced in November 2014 with construction work completed in Kingsthorpe in April 2016 and in Gowrie Junction in May 2016.
  2. Gowrie Junction house connection works commenced in March 2016 and was completed in December 2016.
  3. Kingsthorpe house connection works are scheduled to be completed in August 2017.
  4. Jeude Street sewage pump station, gravity connection and rising main to be constructed and commissioned by end of 2017.